Telstra's multi-billion dollar network and IT transformation project is being driven by the successful implementation of an enterprise program management application that even has the marketing department using it for campaign management, according to the company.
Having spent the past 10 years working on developing standard company processes and the past five on IT systems to support it, Telstra's enterprise program management, or EPM, began to flourish only 18 months ago when CA's Clarity project management application was procured to manage projects over the Web.
EPM is managed by the Telstra Program Office which was established two years ago to drive the company's transformation.
Telstra Program Office lead Carolyn Smart said the division not only drives the transformation of IT work but also how programs and projects are managed across the company.
"EPM is a set of processes supported by a tool and we use EPM for all investment, and that's billions including construction, product development, and marketing," Smart said. "We've manged to convince marketing that a marketing campaign is a project, but we just have to pretend it isn't a project."
Telstra's EPM journey may have started as far back as the mid 1990s, but now 18 months after its installation, 3700 people in the organization are using Clarity to manage about 6500 projects.
"We do not see Clarity as a tool that starts in IT and grows, but see it as a tool across the enterprise," Smart said.
In 2002, before Clarity, IT was asked to help the EPM initiative and built an in-house application called BIMS, which had a workflow engine and automated the approvals process. But the world of project management tended to still live separately at Telstra and most project managers continued to use Microsoft Project, Excel, and the occasional Access database.
The decision to purchase Clarity was motivated by the "plethora of projects around the company" and a desire to use an "out of the box" system.
"Clarity has brought EPM to the project level and we have deployed it across all project management levels to find out the truth and health about a project," Smart said. "We had no centralized company resource management at all. We also use Clarity for benefits realization."
In a presentation on how to effectively govern business initiatives across the enterprise at the 2008 CA Expo in Sydney last week, Smart spoke about how projects at Telstra are executed using a standardized business initiative management framework with four "gating points" and there are some standardized activities for tracking and reporting.
With this methodology, whether it's a marketing or IT project the business case is the same. The project and program status reports have a dashboard view for graphical representation of spending and other metrics.
Other parts of the business process performed in Clarity include parts of sales process, business improvement and baseline programs. It takes people through governance activities and provides project lifecycles.
Computerworld Member Login
Beyond Virtualisation - The Roadmap to 2012
CIO Breakfast Briefing
8:30am - 10:30am
Brisbane | 22 July | Sofitel Brisbane
Sydney | 23 July | Four Seasons Hotel
Canberra | 24 July | The Hyatt
Attend and discover:
- What happens after virtualisation
- The benefits automation drives
- When automated infrastructures will emerge
- What the roadmap to 2012 looks like
- How to deliver an automated architecture
- How to maximise your investment in virtualisation
- +
Computerworld Live Podcast #96: Security at the Edge 11/06/2008 09:22:22
CW Live speaks with Amol Mitra, HP ProCurve Director of Marketing for Asia Pacific and Japan. Today's topic: how enterprises are starting to shift away from simply controlling security via server logins, firewalls and moving to more adaptive security frameworks. - +
Data Management Edition #10: Multi-Petascale Systems 02/05/2008 09:12:33
This week we look at sustainability and the development of multicore technologies to build multi-petascale systems. - +
IT Security Edition #11: How to poison the Storm botnet 01/05/2008 08:51:55
This week CW Live presents a case study on how to poison the notorious Storm botnet . Plus we take a look at Cisco's plans for Ironport. - +
IT Security Edition #10: Cyber-battles fought and won 24/04/2008 11:09:47
Vendors bow to end user pressure to improve product security, and we take a look at the latest concepts shaping the cyber-battlefield of the future. - +
Data Management Edition #9: Data centre makeover 24/04/2008 07:43:06
This week CW Live looks at the death of the old style data centre which is undergoing its first makeover in more than 30 years.
Satyam’s Q1 revenue up by 43% and Net Profit by 45% YoY; revises revenue and EPS guidance upwards for FY09 2008-07-18 16:58:00+10
Informatica Reports Record Second Quarter Results 2008-07-18 13:01:00+10
Tumbleweed Releases MailGate 3.6 2008-07-18 10:01:00+10
Convergys to Acquire Intervoice, Enhancing Leadership in Relationship Management 2008-07-17 14:41:00+10
Borland Management Solutions Put the "M" in Application Lifecycle Management 2008-07-17 13:43:00+10
HP customer perspective white paper: best practices for implementing HP Quality Center software
Discover a structured approach to planning and implementing an integrated, web-based suite of tools. Read on to get practical advice, tools and processes for delivering high-quality applications.