Victorian Ombudsman slams Labor government for failed ICT projects

MyKi, HealthSMART among the projects that cost tax payers $1.44 billion

The Victorian Ombudsman has lambasted the former Labor government for causing major ICT project management issues, with a relaxed approach and inconsistent staff training causing many projects to fail.

In his joint report with the state Auditor General, Victorian Ombusman George Brouwer said state technology projects have made media headlines for all the wrong reasons.

“There have been a number of high profile cost and time blow-outs in ICT and both the Auditor General and I have tabled reports in Parliament that relate to ICT-enabled projects,” Brouwer said in the report.

“These reports have included numerous recommendations for the better management of ICT-enabled projects.”

Making reference to the Baillieu government’s failed MyKi public transport ticketing system and HealthSMART e-health initiative, Brouwer said the former Labor government’s track record for successful IT deployments has been abysmal.

“There has also been wide media coverage over recent years of other government ICT-enabled projects, such as the new public transport ticketing system MyKi and HealthSMART, hich have been criticised for not meeting budget and delivery deadlines and failing to meet expectations,” he said.

“The costs of these systems are significant and have spiralled to levels well beyond those estimated at the commencement of each project.”

Claiming that Victorian taxpayers have been slugged an extra $1.44 billion because of ICT mistakes, Brouwer said the government must comply with industry norms if it is undertake successful ICT projects in the future.

“It is also important in this constantly evolving and changing industry that these principles are regularly reviewed to ensure their ongoing relevance and usefulness,” he said.

Follow Lisa Banks on Twitter: @CapricaStar

Follow Computerworld Australia on Twitter: @ComputerworldAU

More about: Auditor General
References show all

Comments

1

Roger

Fri 25/11/2011 - 12:19

So what? Is anyone responsible losing any sleep (or better yet, their job) over any of this? Of course not and $1.4 billion dollars later the only people laughing are the consultants.

Post new comment

The content of this field is kept private and will not be shown publicly.
Users posting comments agree to the Computerworld comments policy.
Login or register to link comments to your user profile, or you may also post a comment without being logged in.
Related Coverage
Related Whitepapers
Latest Stories
Community Comments
Tags: HealthSMART, ICT projects, Myki, project management, Ted Baillieu, Victorian Department of Transport
Whitepapers
All whitepapers
Sign up now to get free exclusive access to reports, research and invitation only events.
Featured Download
/downloads/product/19/avg-anti-virus-free-edition/

AVG Anti-Virus Free Edition

Note: This review covers version 8.5 of the software. This software is now in version 9.0. Antivirus program AVG 8.5 Free offers solid features and ...

Computerworld newsletter

Join the most dedicated community for IT managers, leaders and professionals in Australia