Sydney Water begins SCADA upgrade
- 22 June, 2010 10:15
- Comments
Three years after announcing it would upgrade Supervisory Control And Data Acquisition (SCADA) systems at its filtration plants, Sydney Water will start an 80-week project scheduled to begin this year at the Nepean catchment.
Five filtration facilities make up the Sydney Water’s Nepean water filtration plant (WFP) cluster, located at Cascade, Orchard Hills, Warragamba, North Richmond and Bargo.
The programmable logic controllers (PLCs) and SCADA network at the Nepean WFP has insufficient redundancy or capacity to add new process sequences, according to Sydney Water.
“The existing PLCs are nearing obsolescence and the procurement of spares is a major problem.”
The Nepean WFP was commissioned in December 1993 and is located near Bargo in the Southern Highlands of NSW. The plant draws raw water from the Nepean Dam and supplies treated water to local towns.
Sydney Water announced a $5 million BI project that would integrate with its SCADA systems in 2008.
More recently, the NSW state-owned corporation was scorned by the auditor-general for a series of multi-million dollar IT project cost blowouts.
Nepean WFP contains 12 PLCs located throughout the plant. The SCADA system has one primary server and another secondary server for control and monitoring of water treatment processes and the upstream raw water pumps.
Other problems with the existing equipment include lack of support, a slow speed network, slow screen updates and an unreliable PLC network.
The project involves an upgrade of existing Citec SCADA to Serck SCX6 SCADA and replacement of PLCs and SCADA LAN network.
Also required is modification of starter circuits in existing motor control centres (MCCs) to suit the Prodef software (Invensys) at the Nepean WFP. The existing MCCs will be kept.
Provision of additional instrumentation and new UPSs is also part of the project, as is a full set of new electrical and SCADA drawings for whole of WFP.
The contract duration is 80 weeks, including testing and commissioning of the overall Nepean WFP SCADA System.
The closing date for interested suppliers is July 29, 2010.
Follow TechWorld Australia on Twitter @Techworld_AU
- Bookmark this page
- Share this article
- Got more on this story? Email Computerworld
- Follow Computerworld on twitter
- Investment Protection and Elasticity for your Network
- So Long, Silos: Why Multi-Domain MDM Is Better For Your Business
- Case Study: NZ Bus Develops Applications 60% Faster, Improves Database Performance by up to 35%
- Case Study: HJ Heinz
- CISO Guide to Next Generation Threats - Combating Advanced Malware, Zero-Day and Targeted APT Attacks
-
Amazon Web Services personalizes CloudFront web hosting service
-
CeBIT 2012: Will NBN speed up freight delivery times?
-
Coalition NBN better or worse?
-
Coalition NBN better or worse?
-
CeBIT 2012: Will NBN speed up freight delivery times?
-
Computers for Seniors for Dummies, 2nd Edition
-
Windows 7 for Dummies®
-
Office 2007 All-In-One Desk Reference for Dummies
-
Microsoft Office
-
MYOB Software for Dummies 6E Australian Edition
-
Teach Yourself Visually Windows 7
-
Excel 2007 All-In-One Desk Reference for Dummies
-
Windows 7 for Dummies® Dvd+book Bundle
-
Windows 7 for Seniors for Dummies®









Comments
Post new comment