Sydney Water blows multiple IT project budgets

$47.2 million in the red and running years behind

The auditor-general, Peter Achterstraat, has flagged several IT project cost blowouts and delays at Sydney Water, including an overspend of $34.3 million on a customer management system.

In the auditor-general's report to parliament 2009 volume seven, which focuses on Environment, Climate Change and Water organisations, Achterstraat identified Sydney Water’s Customer Management System Stage 1 had overshot its original $21 million budget and was now forecast to cost $55.3 million.

The delivery date for the project, which aims to improve customer service, reduce reliance on multiple unsupportable systems and reduce operating costs, had slipped from August 2009 to February 2011.

The significant increase in budget, Achterstraat said, was due to the system integrator costs. Although Sydney Water sought quotes from prospective service providers, the Stage 1 project budget was found to be inadequate.

The change in service delivery date was due to extending the design phase to incorporate proof of concept and extensive review cycles, he said. Extended procurement phases for both content management system (CMS) software and system integrator services also contributed to the variation in schedule.

The organisation’s Maximo consolidation project — aimed at replacing Sydney Water’s current asset management systems — also had significant budgeted overspend. Originally set at $18.4 million, the revised budget had leapt to $31.3 million and its deliver date had fallen behind from August 2009 to October 2010.

“The Corporation underestimated the complexity of the Maximo consolidation project and this is the main reason for the $12.9 million increase in the project budget,” Achterstraat said. “The Corporation advises that the Maximo project is on track to the schedule and budget revised in 2008.”

Its Field Resource Management Stage 2, which is aimed developing a geospatial information system and mobile documents capability, kept its original budget of $7.9 million. Its original delivery date of July 2009, however, had been pushed back to November 2009.

Sydney Water’s Information Management Program — aimed at replacing several disparate document management systems and delivering new systems to better access and share information — was on track for retaining its original budget of $24 million and delivery date of June 2011.

Email Computerworld or follow @computerworldau on Twitter.

More about: CMS, Sydney Water
References show all

Comments

1

Luke

Tue 07/09/2010 - 10:47

This is the worst article i have ever read.

Post new comment

The content of this field is kept private and will not be shown publicly.
Users posting comments agree to the Computerworld comments policy.
Login or register to link comments to your user profile, or you may also post a comment without being logged in.
Related Coverage
Related Whitepapers
Latest Stories
Community Comments
Tags: Auditor-General, cms, information management, project management, sydney water, government, business
Whitepapers
All whitepapers
Sign up now to get free exclusive access to reports, research and invitation only events.
Featured Download
/downloads/product/150/handbrake/

HandBrake

HandBrake is an opensource tool that allows you to backup your DVDs so that you can store and watch them on your computer. Features include: ...

Computerworld newsletter

Join the most dedicated community for IT managers, leaders and professionals in Australia